FY 2017-18 FINAL ADOPTED BUDGET
Infrastructure - Solid Waste Management Fund
BUDGET SUMMARY
2015-16
2016-17 Budget
2017-18 Adopted
2018-19 Projected
Actual
Expenditures:
Personnel Costs
2,208,711 13,274,822
2,290,416 13,841,677
2,362,522 14,485,065
2,432,067 14,658,403
Maintenance & Operations
Capital Outlay
78,000
22,100
0
0
Total
15,561,533
16,154,193
16,847,587
17,090,470
Total FTE Positions
35.580
35.580
35.330
35.330
Revenues:
User Charges Fund Balance
13,391,867 5,898,429
11,615,000 2,286,800
12,265,000 2,371,577
12,265,000 2,614,460
All Other
376,675
355,000
380,473
380,473
Subtotal
19,666,971 1,805,777
14,256,800 1,897,393
15,017,050 1,830,537
15,259,933 1,830,537
General Fund Transfer
Total
21,472,748
16,154,193
16,847,587
17,090,470
BUDGET HIGHLIGHTS The FY 17-18 Budget is increasing by $693,394, or 4.3%. The Budget includes a reduction of $66,856 in the General Fund Transfer from $1,897,393 in FY 16-17 to $1,830,537 in FY 17-18. The FY 17-18 Budget includes a $1,325,000 transfer to the Solid Waste Capital Reserve Fund for post- closure phase III expenses at the Landfill. This is an increase of $1,075,000 from FY 16-17.