CAFR 2017
Schedule 50
Street Improvements Bond Fund - Series 2010 Schedule of Revenues, Expenditures and Changes in Fund Balance - Budget and Actual From Project Inception and For the Fiscal Year Ended June 30, 2017
Actual Current
Project
Prior Years
Total
Authorization
Year
To Date
Revenues:
Miscellaneous: Construction Project Development
$
$
88,683 2,555
$
3,900
$
92,583 2,555
Rent - Real Estate
Total Revenues
91,238
3,900
95,138
Expenditures: Capital Improvements: Transportation
130,941,779
31,917,424
17,491,292
49,408,716
Excess of Revenues Under Expenditures
(130,941,779)
(31,826,186)
(17,487,392)
(49,313,578)
Other Financing Sources (Uses): Debt Issuances: General Obligation Bonds/BANs Issued
134,000,000
35,539,924
18,342,327
53,882,251
Premium on Debt
605,792
(85,193)
520,599
Payment to Escrow Agent for Refunding of Debt
(5,700,000) (2,783,345)
(5,700,000) (3,947,529)
Transfers Out
(3,058,221)
(1,164,184)
Total Other Financing Sources (Uses)
130,941,779
27,662,371
17,092,950
44,755,321
Excess of Revenues and Other Financing Sources Over (Under) Expenditures and Other Financing (Uses)
$
(4,163,815)
(394,442)
(4,558,257)
Fund Balance - July 1
(4,163,815)
Fund Balance - June 30
(4,163,815) $
(4,558,257) $
(4,558,257) $
-109-