Adopted Budget 2015-2016
Infrastructure - Greensboro Transit Authority
PERFORMANCE MEASURES
2013-14
2014-15 Budget
2015-16 Adopted
2016-17 Projected
Actual
Workload Measures Number of passengers (in millions)
4.7
4.8
5.0
5.0
Efficiency Measures Average cost per fixed route passenger Average cost per SCAT passenger
$3.04
$2.85
$2.90
$2.90
32.45
30.00
30.00
31.00
26.50
28.00
28.00
28.00
Passengers per service hour
Percent of customer service requests completed within timeframe
89%
95%
92%
95%
Effectiveness Measures Percent of fixed routes that operated on time Percent of fare cost recovery for fixed route service Percent of fare cost recovery for SCAT service
99%
85%
90%
95%
19%
21%
22%
22%
4%
5%
5%
5%
BUDGET SUMMARY
2013-14
2014-15 Budget
2015-16 Adopted
2016-17 Projected
Actual
Expenditures:
Personnel Costs
741,599
837,028
911,350
936,061
Maintenance & Operations
22,753,997
21,867,800
21,620,887
22,081,191
Capital Outlay
15,700
23,215
0.0
0
Total
23,511,295
22,728,043
22,532,237
23,017,252
Total FTE Positions
12.750
11.750
13.500
13.500
Revenues:
User Charges
2,992,620 7,949,303 1,048,238 8,459,442 2,505,428 1,664,397 1,564,228 26,183,656
3,045,788 6,509,231 1,007,805 8,331,000 1,265,025 1,703,393 22,728,043 865,801
3,060,553 6,462,719
3,060,988 6,462,719
Federal & State Grants Duke Power Contribution
963,754
915,759
Ad Valorem Tax
8,510,000
8,644,000 1,187,316 1,265,025 1,481,445 23,017,252
Appropriated Fund Balance
841,736
Licenses and Permits
1,265,025 1,428,450 22,532,237
All Other
Subtotal
General Fund Contribution
0
0
0
0
Total
26,183,656
22,728,043
22,532,237
23,017,252
BUDGET HIGHLIGHTS
The FY 15-16 Budget for GTA is decreasing by $195,806, or 0.9%. The FY 15-16 Budget uses $841,736 in fund balance and the projected FY 16-17 budget will use $1,187,316 to balance the Transit Fund. This increasing use of fund balance is not sustainable in the long- term. The City will continue to explore options to improve the long-term financial outlook for GTA, including service and fare changes. Three positions from the General Fund are being reallocated to other funds based on time allocation. Two of the positions, totaling 0.75 FTE, are being partially allocated to the Transit Fund at a cost of $31,149. Additionally, a Grants Administrator position was added during FY 14-15.