Adopted Budget 2015-2016
Infrastructure - Engineering & Inspections
Departmental Objectives
Promote a collaborative, efficient and responsive organizational environment that supports the needs of citizens, businesses and developers in the Greensboro area. Provide for the construction of City resources to support desired growth or a quality of life that is attractive to economic development.
Maintain City assets and resources to provide efficient and effective municipal services.
Take measures to ensure regulatory compliance standards are met.
Provide a safe transportation system that ensures mobility for all users. Develop and implement strategies to promote environmentally sound practices.
Identify and implement cost saving measures and increase revenue generating opportunities. Provide cost efficient inspection services as compared with other North Carolina jurisdictions. Provide support to public safety personnel and residents. Provide training and certification opportunities to employees. Complete work orders and mission critical functions within departmental adopted standards. Support and promote City services and communicate effectively with both internal and external customers. Develop and manage departmental budgets that efficiently provides for quality service to meet the demands of the community.
Promote and educate employees on workplace safety.
PERFORMANCE MEASURES
2013-14
2014-15 Budget
2015-16 Adopted
2016-17 Projected
Actual
Workload Measures # of plan reviews conducted # of work orders completed # of City facility audits performed # of roadway footage inspected # of linear feet of new sidewalk installed
1,420
1,235
1,235
1,235
72,414
69,630
69,630
69,630
81
83
83
83
226,158
100,000
100,000
100,000
100,120
80,000
80,000
80,000
Efficiency Measures Average cost per plan review % of major facilities audited
$378
$465
$465
$465
100%
100%
100%
100%
% of City of Greensboro inspection costs compared to other jurisdictions
56.8%
60.5%
60.5%
60.5%
Average # of inspections per day per inspector
18.1
17.2
17.2
17.2
Effectiveness Measures % of plan reviews completed within time commitments
99%
98%
98%
98%
% of work orders completed on time
77%
86%
89%
89%
% of construction projects completed within targeted timeline % of trades inspections completed within targeted time frame Average grade for facilities capital renewal maintenance
83%
95%
95%
95%
82%
92%
92%
92%
-
C-
C
C
Adopted FY 2015-16 Budget
76