5
General Requirement, 5% 3
$ 750.00
Subtotal
$ 15,750.00 $ 420.00 $ 1,575.00 $ 315.00 $ 1,575.00 $ 19,635.00 $ 2,945.25 $ 22,580.25 $ 2,790.92 $ 25,371.17
Sales tax, 7% 1
Construction Contingency, 10% 3
Bonds, Insurance, 2% 3 Design Contingency, 10% 3
Subtotal
GC Overhead/profit, 15% 3
Subtotal
Escalation, 6% / yr x 8 yrs. = 1.48
Phase 4 Total
1. Sales tax on materials only, not labor. Assume labor equates to about 40% of total costs 2. Assumed structures without a conceptual design 3. Assumed percentages. 4. The category of other was lumped in the Phase 1 totals
Total Project Construction Cost over 4 Phases =
$ 8,412,564.08