Continue to develop joint development opportunities with the private sector at the J. Douglas Galyon Depot. Complete work orders and mission critical functions within departmental adopted standards. Support and promote City services and communicate effectively with both internal and external customers. Identify and implement cost saving measures and increased revenue generating opportunities. Identify and secure outside funding. Promote and educate employees in workplace safety and wellness. Provide training and certification opportunities to employees. Develop and maintain a safe transportation system. Provide a safe transportation system that is effective to all users. Provide quality customer service. Adminster development plan review process within the department. Conduct departmental services in a manner that ensures fiscal stewardship. Conduct transportation planning activities which support economic development focus areas.
PERFORMANCE MEASURES
2016-17
2017-18 Budget
2018-19 Adopted
2019-20 Projected
Actual
Workload Measures Number of high accident locations studied
29 30
30
30
Number of streetlights inspected along major travel corridors 3,800
5,400
5,400
5,400
Number of linear feet of new sidewalk installed
21,035
20,000
20,000
20,000
952
900
900
900
Number of plan reviews conducted
Number of special events requiring Transportation maintenance services
192
120
190
190
Efficiency Measures Average cost per plan review
$230
$240
$230
$230
Effectiveness Measure
88%
91%
90%
90%
Percent of GDOT workorders completed on time Percent of GDOT maintenance completed on schedule Percent Public Information Requests completed within two days
69%
92%
90%
90%
78%
90%
90%
90%
BUDGET SUMMARY
2016-17
2017-18
2018-19
2019-20
Actual
Budget
Adopted
Projected
Expenditures:
Personnel Costs
4,103,398 5,797,033
4,296,576 5,965,983
4,386,513 6,009,257
4,480,314 6,090,073
Maintenance & Operations
Capital Outlay
24,008
0
0
0
Total
9,924,438
10,262,559
10,395,770
10,570,387
Total FTE Positions
59.426
58.926
58.926
58.926
Revenues:
Fines and Forfeitures State Maint. Fees Licenses & Permits Rents & User Fees
1,782,826
1,790,000
1,580,000
1,580,000
453,275 82,208 302,383 125,349
707,000 68,000 367,788 90,800
707,000 69,000 374,052 130,800
707,000 69,000 380,316 130,800
All Other
Subtotal
2,746,041 7,178,397
3,023,588 7,238,971
2,860,852 7,534,918
2,867,116 7,703,271
General Fund Contribution
Total
9,924,438
10,262,559
10,395,770
10,570,387
BUDGET HIGHLIGHTS The FY 18-19 Budget is increasing by $133,211, or 1.3%.
An additional $38,861 is included in the Street Lighting budget in FY 18-19 to cover increasing utility costs, including the additional cost of LED lighting put in by Duke Energy to replace old lighting as well as new lighting installed when street projects are completed around the city.